Temporary road closure at various locations of M18/N18

15 July 2025

UPDATED

Week 7

  • Monday 29th September – 7pm to 6am – M18 Southbound Phase E - Junction 7 On-Slip Closed and J6 (Bunratty North) on and off-slips closed – Plans Ref:CJV-G2-DR-SK-2702 to 2704
  • Tuesday 30th September – 7pm to 6am – M18 Northbound Phase A - Junction 6 On-Slip & 7 Off-Slip Closed–Plans Ref:CJV-G2-DR-SK- 2671
  • Wednesday 1st October – 7pm to 6am – M18 Southbound Phase C – J10 to J9 Closed–  Plan Ref:CJV-G2-DR-SK-2689 attached
  • Thursday 2nd October – 7pm to 6am – M18 Northbound Phase C – J19 to J10 Closed–  Plan Ref:CJV-G2-DR-SK-2675 attached

SCHEDULE OF WORKS

Week commencing 22nd September 2025

  • Monday 22nd September – 7pm to 6am – M18 Northbound Closed between J7 & J9, with an Up & Over at J6 and HS running to J7– Diversion Plan Ref:CJV-G2-DR-SK-2673 attached below
  • Tuesday 23rd September – 7pm to 6am – M18 Southbound Closed between J9 & J7, with HS running to J6 and Closed between J6 & J6A – Diversion Plan Ref:CJV-G2-DR-SK-2692 & 2693 attached below
  • Wednesday 24th September – 7pm to 6am – M18 Southbound Junction 7 On-Slip Closed and J6 (Bunratty North) on and off-slips closed – Diversion Plan Ref:CJV-G2-DR-SK-2703 & 2704 attached below
  • Wednesday 24th September – 7pm to 6am – M18 Northbound Junction 7 Off-Slip Closed– Diversion Plan Ref:CJV-G2-DR-SK-2671 attached below

Week commencing 29th September 2025

  • Monday 29th September – 7pm to 6am – M18 Southbound Phase E - Junction 7 On-Slip Closed and J6 (Bunratty North) on and off-slips closed – Plans Ref:CJV-G2-DR-SK-2702 to 2704
  • Tuesday 30th September – 7pm to 6am – M18 Northbound Phase A - Junction 6 On-Slip & 7 Off-Slip Closed–Plans Ref:CJV-G2-DR-SK- 2671
  • Wednesday 1st October – 7pm to 6am – M18 Southbound Phase C – J10 to J9 Closed–  Plan Ref:CJV-G2-DR-SK-2689 attached below
  • Thursday 2nd October – 7pm to 6am – M18 Northbound Phase C – J19 to J10 Closed–  Plan Ref:CJV-G2-DR-SK-2675 attached below

Notice is hereby given in accordance with Section 75 of the Roads Act 1993 of Clare County Council’s decision to close the roads detailed hereunder for the period stated to facilitate lining, studs and pavement repairs.

Roads to be closed:

M18/N18 Northbound                                                         M18/N18 Southbound

1. N18 between J6 On & Off Slips 1. M18 between J14 and J12
2. N18 J7 Off-Slip 2. M18 J13 On-Slip
3. N18 between J7 and J9 3. M18 between J12 and J11
4. M18 between J9 and J10 4. M18 between J11 and J10
5. M18 between J10 and J11 5. M18 between J10 and J9
6. M18 between J11 and J12 6. N18 between J9 and J7
7. M18 between J12 and J14 7. N18 between J6 and J6A
8. M18 J13 On-Slip 8. J7 On-Slip
9. J6 On-Slip
10. J6 Off-Slip


Date and time of closures:
Daily for  period not exceeding 7 nights per closure, between the dates of 18th August 2025 and 29th November 2025 between the hours of 7:00 p.m. and 6:00 a.m.

Alternative routes/diversions: drawings attached below

M18/N18 Nothbound                                                           M18/N18 Southbound

1. J6 Off-Slip, J6 On-Slip (drawing 2673) 1. J14, R458, R352, N85, J12 (drawing 2775 & 2776)
2. N18 to J8, R471 (drawing 2671) 2. J13, R352, R871, R458, N85, J12 (drawing 2765)
3. J7, R471, R472, N19, J9 (drawing 2673) 3. J12, N85, R458, J11 (drawing 2685)
4. J9, R458, R472, J10 (drawing 2675) 4. J11, R458, R472, J10 (drawing 2687)
5. J10, R472, R458, J11 (drawing 2677) 5. J10, R472, R458, J9 (drawing 2689)
6. J11, R458, N85, J12 (drawing 2679) 6. J9, N19, R472, R471, J7 (drawing 2692)
7. J12, N85, R352, R458, J14 (drawing 2773) 7. J6, L3122, J6A (drawing2693)
8. J13, R352, R871, R458, J14 (drawing 2774) 8. R471, R458, J9 or R471, J8, N18 North, J9 (drawing 2703)
9. L3122, J6A (drawing 2704)
10. J6A, L3122 (drawing 2704)

 

Page last updated: 26/09/25