Latoon Creek Bridge Rehabilitation - Progress Update 08/03/18

Date issued: 08/03/18

L & M Keating Ltd. is continuing works at Latoon Creek Bridge, located on the R458 south of Clarecastle. Repairs to the piers and abutments are complete.
The 1200 Tonne crane has returned to site on schedule to lift in the 43 Tonne precast centre span beams. These beams will be delivered to site tomorrow. The remainder of the beams will be installed in the coming weeks.  Works are on schedule.